04.28.16
Harris, in coordination with the Central Arizona Project (CAP), replaced the existing water-cooled chillers with air-cooled chillers at the Brady, Picacho and Red Rock Pumping Plants on the CAP Aqueduct.
Harris operated in a prime contracting role and self-performed the mechanical scope. This project included the removal of the existing chillers, installation of new chillers, replacement of piping and specialties, and HVAC renovations. Subcontracts were let for electrical power wiring to serve the new equipment, temperature controls, ...
Read More
12.07.15
Music City Center is a 2,100,000-square foot gathering space featuring an exhibit hall, grand ball room, meeting rooms and parking complex.
Harris teamed with longtime partner Foley Company, to fabricate and install 2,400,000 pounds of sheet metal for the HVAC ductwork. Harris also furnished and installed 62 air handling units totaling more than 1,800,000 cubic feet per minute of ventilation.
The immense fabrication effort required 35,500 shop hours which was accomplished by Harris’ Utah fabrication facility and a local ...
Read More
12.07.15
The new six-story, 790,000-square foot Veterans Affairs Medical Center represents the largest construction contract ever awarded by the United States Department of Veteran Affairs. The hospital provides complete medical services, including ambulatory care, radiology, laboratories, pharmacy, diagnostic and treatment clinics, and educational facilities.
Harris fabricated and installed 1,900,000 pounds of ductwork for Phase IV of the $364.9 million hospital project. Partially staffed on-site, Harris’ BIM team met weekly to coordinate with other trades for interference, using the project model ...
Read More
12.07.15
The Sutter Health Eden Medical Center is a 130-bed, acute care hospital totaling 230,000 square feet. The new state-of-the-art next generation healthcare facility was built to exacting standards developed through an integrated planning process with the construction, design and patient care team that ensured alignment of clinical program elements, building and healthcare features and community goals.
Harris completed the project around existing hospital traffic and activities, while working to cause minimal disruption. During preconstruction, BIM/VDC along with ...
Read More
12.07.15
Utilizing Lean construction techniques and an integrated project delivery shared risk/reward contract, Harris performed design-assist HVAC and virtual design and construction (VDC) services for the new Alta Bates Medical Center Merritt Pavilion. The new, 250,000-square foot medical facility is a state-of-the-art medical/surgical patient tower with acute rehabilitation services, on-premises pharmacy and nuclear medicine. This iconic building also brings the campus into compliance with California’s strict seismic safety requirements.
The Merritt Pavilion was designed to ...
Read More
10.05.15
Harris provided the HVAC sheet metal required for Los Angeles International Airport’s overhaul of their central plant. Overall, Harris fabricated 120,000 pounds of sheet metal for the project and ensured proper procedures were followed for the client’s LEED Gold certification goals.
The transportation of people and equipment was a major challenge for the project team. The lay down area was five miles away from the project site through heavy traffic. To reduce time spent on the ...
Read More
07.17.14
The new GateWay Community College (GCC) Integrated Education Building was designed to house five separate programs in uniquely recognizable structures that connect, integrate and function as one building. Built to LEED standards, the three-story building features offices for student services, counseling and advising, an indoor/outdoor art room, new library, tutoring labs, additional classrooms and a new science wing.
To cool the building, Harris brought new 14-inch chilled water lines across the campus via an underground utility ...
Read More
07.10.14
The University of Kentucky’s (UK) new Pavilion A at the Albert B. Chandler Hospital is the cornerstone of a 20-year construction plan for this academic medical campus of the future. This 1,100,000-square foot hospital was completed in two phases, allowing for the step-by-step replacement of the hospital’s existing pavilion. Areas included an emergency department, surgery center, trauma center, radiology, specialty floors and patient rooms and an auditorium.
Harris performed the HVAC build-out for this facility, ...
Read More
07.10.14
The 52-story Devon Tower is one of Oklahoma City’s most visible landmarks and was designed as an office headquarters for Devon Energy, but also a place for people to enjoy dining and views from the upper floors. This high profile, LEED Gold certified skyscraper presented Harris with major challenges. With so many floors to traverse, the coordination of materials and the vertical transportation of work force, became a major organizational hurdle for all the trades to coordinate.
Read More
07.10.14
On November 18th, 2016, the Southeast Louisiana Veterans Health Care System celebrated the grand opening of its New Orleans medical center with a ribbon cutting. Harris manufactured and installed more than 2,000,000 pounds of ductwork for the new medical campus and provided design-assist services.
This is the second major Veterans Affairs (VA) hospital project Harris has performed with general contractor partner Clark Construction, the first being the VA Medical Center in Las Vegas.
After Hurricane Katrina in 2005, ...
Read More