08.11.20
The Reagan National Airport New North Concourse is a three-level, 230,000-square-foot, $374 million concourse, which is part of a larger $1 billion terminal redevelopment plan at Ronald Reagan Washington National Airport in Arlington, Virginia. The new 14-gate concourse will replace onsite bus service to regional carriers with passenger bridges, keeping travelers out of the elements and giving them easier access to flight information and new amenities like retail, food, an airport club and device-charging outlets. There will also be a new ...
Read More
08.11.20
Harris was chosen to install the plumbing and HVAC for the Prescott VA Mental Health Building. The plumbing systems were cast iron underground waste piping, cast iron above ground waste and vent piping. The domestic water systems are standard copper with re-circulated hot water systems. The systems did not require any special medical gases or special equipment, making installation easier.
On the HVAC side, Harris installed a 48 well geothermal piping system, including site piping to the mechanical ...
Read More
08.11.20
Harris performed the complete mechanical installation for Southern Minnesota Municipal Power’s 38.8 MW natural gas-fired power plant in Owatonna, MN. The plant was designed to replace the power generating capacity the city lost during a flood in 2010. The plant consists of four new Caterpillar 10 MW gas-fired generators as well as related piping and equipment.
Harris installed the engine support piping which included air piping, lube oil piping, natural gas piping, used oil piping, glycol piping and cooled ...
Read More
08.11.20
Harris was awarded the contract for the new ESPN Studio at The Linq Hotel along the Las Vegas Strip. The project will include 2,300 square feet of new studio space and 2,400 square feet of renovated office space. The new studio will be ESPN’s Vegas hub during major sporting events along with other related content.
Harris will provide both HVAC and plumbing for both the studios and office space. There will be three different studios built that overlook ...
Read More
08.11.20
SLC4 is DataBank’s 3rd data center to open on the Granite Point Campus and became fully occupied within months of opening, a testament to the high-demand for its world-class capabilities. Located in Bluffdale, UT, minutes from downtown Salt Lake City and Utah’s “Silicon Slopes” technology hubs, SLC4 provides 20,000 square feet of raised-floor space, the facility offers network connectivity to over a dozen carriers and cloud providers, as well as access to Granite Point’s own private 66MW ...
Read More
08.11.20
Harris was awarded the HVAC and plumbing package for the new Churchill Downs race and Gaming Facility in Oak Grove, Kentucky. This face-paced project includes a 150,000-square-foot gaming and entertainment venue, a 128-room hotel, race-day and overnight stables, an equestrian center, amphitheater, an RV park and maintenance buildings.
Harris will install 24 miles of pipe and 380,000 pounds of sheet metal duct during the underground plumbing work. This will require approximately 80 craft workers at peak manpower to meet the ...
Read More
08.11.20
Harris was hired as the mechanical contractor for the Aligned Energy Data Center by Okland Construction. Aligned Energy is an infrastructure technology company that offers colocation and build-to-scale solutions to cloud, enterprise, and managed service providers. The company strives to utilize intelligent infrastructure to deliver data centers like a utility—accessible and consumable as needed.
Prefabrication was a key factor in the success of this project. In a matter of minutes, the team was able to install 200’ ...
Read More
08.11.20
The new Alex G. Spanos Heart & Vascular Center was built to address growing community needs. The new 123,000-square foot, four-story facility has space for innovative technology and increased patient capacity.
Throughout preconstruction, the project team successfully collaborated and resolved logistical complexities associated with an extremely tight site, design redirection and modifications to the project. The team overcame the obstacles associated with a very limited project space and the challenges associated with working in a operational medical ...
Read More
08.11.20
In spring of 2018, Harris installed a new ammonia compressor, intercooler, and new piping and accessories at the Birdseye Plant in Waseca, MN. As part of this project, Harris demolished and removed several existing system components and installed a new compressor and intercooler as stated above. In addition, there were several pieces of equipment that had to be relocated within the plant in order for the new equipment to be installed. Harris worked closely with the owner, engineer, and equipment ...
Read More
08.11.20
Harris performed the installation of all heating, cooling, and process piping on a nearly 1,000,000 square foot expansion project at the Faribault Foods Plant in Faribault, MN. As part of the project, Harris installed two 1000 BHP boilers, two 550-ton chillers, three cooling towers, three large outside water storage tanks, and all of the other associated pumps and piping specialties related to each of the piping systems installed. Along with this, Harris also ran several thousand feet of steam, condensate, chilled ...
Read More